Demolition Method Statements: What Should They Include?
A demolition method statement should explain the specific work, the information it relies on, the planned sequence, how stability will be maintained, and the controls protecting workers and other people. It also needs clear responsibilities, checks before work proceeds, emergency arrangements and a process for changes. A generic list of hazards is not a usable demolition plan.
This guide helps clients, supervisors and learners review the completeness of the document. It concerns Great Britain and does not provide a demolition sequence, structural design or authority to carry out work. Those decisions require competent, project-specific planning.
What is legally required, and what does the statement do?
CDM 2015 regulation 20 requires demolition or dismantling to be planned and carried out to prevent danger, or reduce it as low as reasonably practicable where prevention is impracticable. The arrangements must be recorded in writing before work begins. The regulation does not prescribe a universal form or page count.
A risk assessment identifies and evaluates risks; the method statement explains the working arrangements that address them. The construction phase plan coordinates the wider project. These documents should agree rather than offer competing instructions. HSE's method-statement guidance explains their practical relationship and the value of a logical sequence with controls built in.
For example, “falling debris” identifies a hazard. The method statement needs to show how the proposed operation controls it, where people may be, and what prevents anyone entering the danger area. A signature cannot compensate for missing arrangements.
Establish the information and its limits
Begin with an evidence register: structure and location, scope boundaries, relevant surveys, drawings, previous alterations, neighbouring property and services information. Give each important reference a revision or date. Record missing information explicitly instead of allowing an assumption to become an apparent fact.
HSE says the demolition method must be prepared by a competent person and the contractor's scheme reviewed by a competent engineer before work starts. Its demolition guidance also identifies structural form, load paths, site constraints and available space as factors in choosing the method. A previous project's document cannot establish those conditions on this site.
A useful document-control question is: “Which instruction would change if this survey finding were different?” If the answer is unclear, the survey may have been attached without its findings being incorporated.
Use a document checklist that leads to decisions
The following is an editorial review aid, not a statutory template or technical approval checklist. Each row should point to actual project information, with an owner for unresolved items. The document may use different headings provided the arrangements remain clear.
| Document section | What the reviewer should be able to locate |
|---|---|
Identity and scope | Site, work areas, retained elements, exclusions, author, revision and applicable drawings. |
Evidence and assumptions | Survey findings, limitations, unanswered queries and who resolves them. |
Method and stages | Defined operations, stage boundaries, interfaces and references to the engineered scheme. |
Stability and temporary works | Design references, restrictions, checks and authority for changes or release. |
People and equipment | Roles, competence requirements, supervision, plant suitability and instructions. |
Protection and logistics | Controlled areas, access, debris handling, public interfaces and changing layouts. |
Health and emergencies | Task-specific exposure controls, inspection arrangements, emergency actions and rescue where relevant. |
Release and revision | Required checks, outstanding restrictions, briefing records and restart authority. |
Make stability and working zones explicit
The document should reference the competent assessment and any temporary works design rather than ask operatives to invent support arrangements. HSE's structural-stability guidance explains that foreseeable loading includes machinery and accumulated debris. Supports require appropriate design, installation, checking, inspection and maintenance.
Do not treat ordinary access scaffold as structural restraint. Removing part of a structure can change how loads reach the ground and how the remaining structure resists sideways forces. Any necessary support and its removal must follow the designer's requirements.
Show safe working, exclusion and debris areas on a readable drawing, including how they change between stages. HSE's demolition guidance makes their extent dependent on the method, space and possible debris travel; it does not offer one distance suitable for every building. Where containment cannot be achieved, the method needs reconsideration. Coordinate vehicle routes and neighbouring activities with the site logistics arrangements.
Resolve asbestos and service risks before disturbance
A normal asbestos management survey is not a substitute for a suitably scoped refurbishment or demolition survey. HSE's survey guidance explains that this intrusive survey must identify hidden asbestos-containing materials before structural work and be undertaken by a competent surveyor. Asbestos must be removed, as far as reasonably practicable, before major refurbishment or demolition.
Record survey coverage and access restrictions, the required specialist work and the evidence needed before the affected area is released. If suspect material is discovered, stop disturbance and obtain competent assessment; do not add “wear a mask” and continue.
Identify services that could be affected, who controls them and what evidence establishes the required safe condition. HSE's concealed-services guidance stresses obtaining service information and locating services before work that may strike them. An old drawing alone is not a verified isolation.
Check access routes as well as the demolition footprint. HSE's overhead-line guidance warns that close approach can cause flashover without contact. Consult the line owner about avoidance, diversion, isolation or suitable controls. Do not invent a clearance from a photograph or assume a line is dead because the building is unoccupied.
Include health controls and workable emergency arrangements
Identify dust-generating tasks and materials, including concrete and mortar that may produce respirable crystalline silica. HSE's construction-dust guidance, CIS36 revision 3, prioritises preventing or reducing dust and controlling its release. Depending on the assessed task, controls may include suitable water suppression or extraction, supported by appropriate respiratory protection. Tight-fitting RPE needs face-fit testing. A disposable mask alone is not a complete dust-control system.
Specify how controls are supplied, checked and maintained, and what happens if they fail. Include relevant noise, vibration, fire, handling and hazardous-material assessments. No chemical product is prescribed here: the actual project must use the selected products' current safety data sheets and equipment instructions.
Where work at height remains necessary, apply the hierarchy of avoidance, fall prevention and mitigation. Identify access and fragile-surface controls. HSE's work-at-height guidance also requires emergency and rescue planning; it says arrangements should not rely on the fire brigade. The method statement should identify the practical arrangements and competent resources, not merely list an emergency telephone number.
Plan waste handling alongside these controls. The hazardous construction-waste guide explains identification and records for England; use the relevant national rules for other locations.
Brief, monitor and revise the working document
As a practical review method, pair every critical control with four fields: required condition, evidence, responsible person and action if absent. For instance, an unresolved survey restriction should have a clear affected area and decision owner. “To be confirmed” is an open issue, not permission to proceed.
Brief the people doing the work using the current document and drawings. Ask them to explain their work boundary, communication arrangements and stop conditions. A collected signature records attendance; it does not by itself demonstrate understanding. Check actual practice against the document, and revise the arrangements when conditions change materially, as HSE's method-statement guidance advises.
Illustrative example: a team uncovers a connection that is absent from the surveyed drawings. The supervisor stops the affected activity and reports the discrepancy. The competent team assesses its significance, updates the scheme and linked documents as necessary, and defines the conditions for restart. Workers receive the revised briefing before release. This fictional example illustrates change control; it is not a method for altering that connection.
Before accepting the document for use, check for stale drawing references, conflicting layouts, controls with no owner and unresolved design queries. People exploring the occupational pathway can compare their actual role with the Level 3 demolition qualification. A qualification does not replace project-specific engineering, supervision or authorisation.
Editorial scope and sources
Prepared with substantial AI assistance in research and drafting, using the linked primary sources checked on 21 November 2026. Checks covered source support, scope, internal consistency and document completeness. No named human contribution, independent demolition-engineer review or firsthand project evidence has been verified. The featured image is AI-generated and illustrative. This is a document-review guide; a competent project team must develop and review the actual demolition arrangements. Planning, building-control and other permissions must be checked separately for the location and work.
Frequently Asked Questions
CDM regulation 20 requires written arrangements before demolition or dismantling begins, but does not prescribe one form. Use a structure that communicates the actual arrangements and responsibilities clearly.
Its headings may be useful, but reassess the evidence, method, constraints and controls for the new project. A different structure or setting may need substantially different arrangements.
No. Required surveys, reviews, controls and other applicable permissions must also be in place. Document acceptance does not establish that every site condition has been satisfied.
Stop the affected activity, make the situation safe within the agreed arrangements and refer it to the responsible competent people. Resume only after the required assessment, revision and briefing.